The timeline for this project will be updated with more details as they are known. Dates and times are subject to change and can be weather dependent.
-
November 2022- Removal of the original Fountain of the Four Seasons sculpture for conservation and replication.
-
November 2022-July 2023- Offsite replication and conservation of the Maidens.
-
Spring 2023- Construction on the fountain site at the Memorial Union, with work to stabilize the pool structure, increase water use efficiency, and update water filtration system.
-
Fall 2023: Replicated Maidens and terra cotta ring installed. The pool will remain unfilled for the season to allow time for materials to properly cure.
-
Spring 2024: Filling of the fountain.